Projects
New Development Whitewell Road, Belfast
- Ark Housing Assoication
- £1,470,000.00
- 70 weeks
- Harry Roulston Architects
New Development Springfield Avenue, Belfast
- Oaklee Housing Association
- £1,176,000.00
- 52 weeks
- Harry Roulston Architects
Apartment Block University Avenue, Belfast
- SHAC Housing Assoication
- £800,000.00
- 52 weeks
- Dempsey Architects
Freehall and Rockmount, Coleraine
- Northern Ireland Housing Executive
- £2,196,000.00
- 105 weeks
- Cooke and Kettyle
Monkstown Phase 5, Belfast
- Northern Ireland Housing Executive
- £1,480,000.00
- 77 weeks
- Parkman Cairns Moore Consortium
Carisle Multi Storey Flats
- Northern Ireland Housing Executive
- £777,000.00
- 52 weeks
- V B Evans and Company
Planned Maintenance at Giboney Court Cookstown
- Clanmill Housing Association
- £477,000.00
- 36 weeks
- The FCM Partnership
Apartment Block at Woodland Avenue, Belfast
- Flax Housing Association
- £750,000.00
- 70 weeks
- McKenna Design Architects
Group Repairs Omagh
- Northern Ireland Housing Executive
- £430,000.00
- 52 weeks
- Hood McGowan Kirk
Multi Element Improvements Kilcooley Phase 5
- Northern Ireland Housing Executive
- £1,535,000.00
- 100 weeks
- V B Evans and Company
Group Repairs Newinton Phase 2
- Northern Ireland Housing Executive
- £572,000.00
- 52 weeks
- W H Stephens
Improvement Works at Lower Braniel, Belfast
- Northern Ireland Housing Executive
- £664,000.00
- 64 weeks
- A G Crawford
DDA Alterations to Various Properties
- Wesley Housing Association
- £205,000.00
- 20 weeks
- W H Stephens
Servia Street, Belfast
- Habintag Housing Association
- £320,000.00
- 40 weeks
- Northern Ireland Housing Executive
Lift Replacement Twickenham House
- Northern Ireland Housing Executive
- £255,000.00
- 30 weeks
- McCutcheon and Wilkinson
Group Repairs Northwood Phase 1
- Northern Ireland Housing Executive
- £510,000.00
- 52 weeks
- Michael Herron Architects
Group Repairs Northwood Phase 2
- Northern Ireland Housing Executive
- £370,000.00
- 40 weeks
- Michael Herron Architects
Improvement Works at Ardnagrenna, Holywood
- Northern Ireland Housing Executive
- £680,000.00
- 54 weeks
- McCutcheon and Wilkinson
External Cyclical Maintenance Ainsworth and Woodvale
- Northern Ireland Housing Executive
- £382,000.00
- 40 weeks
- W H Stephens
Parkgate Re-Improvement Scheme
- Connswater Housing Association
- £250,000.00
- 26 weeks
- JCP Consulting
Cyclical Maintenance to Various Locations
- Belfast Community Housing Association
- £120,000.00
- 18 weeks
- Hall Black Douglas
Refurbishment Works at Station Road Glenarm
- Oaklee Housing Association
- £104,000.00
- 12 weeks
- The FCM Partnership
Group Repairs Beechmount Phase 6
- Northern Ireland Housing Executive
- £453,000.00
- 36 weeks
- V B Evans and Company
Environmental Improvements Sandy Row Belfast
- Northern Ireland Housing Executive
- £479,000.00
- 44 weeks
- BDP Architects
External Cyclical Maintenance at Mount Vernon Belfast
- Northern Ireland Housing Executive
- £287,000.00
- 30 weeks
- Cooke and Kettyle
Environmental Improvements at Colinbrook Estate, Belfast
- Northern Ireland Housing Executive
- £680,000.00
- 52 weeks
- BS Design Consultants
Major Disability Adaptations to Various Properties
- Northern Ireland Housing Executive
- £93,000.00
- 18 weeks
- Northern Ireland Housing Executive
Health and Safety Works at DLO Depot Pennyburn
- Northern Ireland Housing Executive
- £52,000.00
- 9 weeks
- P F Corr Limited
Dufferin Avenue Flat Conversions
- Ulidia Housing Association
- £96,000.00
- 20 weeks
- Building Projects
Replacement of Communal Floor Coverings at Ballydown Court
- Oaklee Housing Association
- £30,000.00
- 3 weeks
- Oaklee Housing Association
Cranley Road Bangor
- BIH Housing Association
- £15,000.00
- 6 weeks
- A G Crawford and Company
Gallaun Court Downpatrick
- Clanmill Housing Association
- £32,000.00
- 10 weeks
- The FCM Partnership